What’s New? Alverno has moved out of the LA demolition locations, and the first phase of demo in the LA building has started. The first phase of LA includes first floor southwest, first floor north, and second floor north. Drywall is up in the kitchen, overhead mechanical/electrical/plumbing work continues. The Past Week • Above ceiling demolition in the
...
What’s New? Classrooms and offices are framed in the first phase of the LA remodel. The majority of Mechanical/Electrical/Plumbing in wall work has been completed. The concrete stage has been poured in the new commons building. The Past Week • Kitchen flooring is being installed. • Framing in first phase of LA is complete. • Fireproofing in N2
...