PROJECT TIMELINE

Dates are subject to change. Bookmark promise & power for regular updates and current timeline information.

Alverno College-Master Plan Phase 1 August 28th, 2014

Posted: August 29, 2014

What’s New?

Phase 1 is complete, and new areas are open for Fall ‘14 classes.

The Past Week

• Construction barriers have been removed.
• Office furniture has been installed.
• The newly renovated kitchen is up and running.
• Faculty has moved into new offices.
• New classes have begun in areas of Founders Hall.

Coming Up in the Weeks Ahead

• Café will be open for business.
• Ability column logos to be installed.
• Commons divider wall to be installed.
• Library divider wall will be complete.
• Major progress on Alexia Hall.

Fun Fact: The new commons building was built in 164 days (ground breaking to turnover to Alverno).

Alverno's new servery, "Hudson's"

The new servery, “Hudson’s”

Alverno Commons program space and logo store

New program space with the logo store behind

Alverno College New Commons Grand Opening

Grand Opening of the New Commons

New Commons Lounge & Fireplace

Commons Lounge Area & Fireplace

To learn more about how you can get involved in this transformational campaign for Alverno's future, please contact Kaye Leszczynski in the Advancement Office at (414) 382-6095 or kaye.leszczynski@alverno.edu. Thank you for your interest in and support of Alverno College!