Executive Summary Report August 3, 2015

Posted: August 3, 2015

What’s New?

Construction is winding down as the start of the fall semester is approaching. Findorff and Alverno will begin a series of “punchlists” for newly completed areas beginning in early August. During punchlist walk-throughs, Alverno points out anything that needs to be repaired or changed before moving in.

The Past Week

• Completion of FO 3rd floor classrooms.
• Completion of AF 2nd floor offices.
• Concrete curbs poured in the Pitman lot.

Coming Up in the Weeks Ahead

• Asphalt paving in Pitman lot and loading dock – starting Monday 8/3.
• Landscaping throughout areas of construction.
• Substantial completion of all phases of construction.

Fun Fact: The final landscaping throughout campus will begin on Monday 8/10, and be completed in 16 working days (weather pending).

New walking path from Alexia to RC/AF

New walking path from Alexia to RC/AF

Sidewalks are poured outside of Alexia Hall

Sidewalks are poured outside of Alexia Hall

Curbs are poured in the Pitman lot

Curbs are poured in the Pitman lot

RC loading dock is ready for asphalt

The RC loading dock is ready for asphalt