Executive Summary Report – December 2, 2014
What’s New?
The exterior windows have been installed, all openings have been sealed, and the heat is up and running in Alexia Hall!
The Past Week (Alexia Hall)
• Elevator installation is complete.
• Drywall work continues.
• Concrete floor polishing on the ground level has started.
• Painting has begun on the ground level.
• Fireproofing is taking place at the Christopher Hall/Alexia Hall connection.
Coming Up in the Weeks Ahead (Alexia Hall)
• Cabinets will be installed.
• Acoustical ceilings will be hung.
• Floor finishes will begin to be installed.
• Doors/hardware we be installed.
• Furniture will begin to be moved into classrooms.
Fun Fact: The polished concrete floor finish on the ground level of Alexia Hall requires low maintenance, is stain-resistant, and can be polished in ranges of low to high sheen in a variety of colors.