Executive Summary Report – December 2, 2014

Posted: December 2, 2014

What’s New?

The exterior windows have been installed, all openings have been sealed, and the heat is up and running in Alexia Hall!

The Past Week (Alexia Hall)

• Elevator installation is complete.
• Drywall work continues.
• Concrete floor polishing on the ground level has started.
• Painting has begun on the ground level.
• Fireproofing is taking place at the Christopher Hall/Alexia Hall connection.

Coming Up in the Weeks Ahead (Alexia Hall)

• Cabinets will be installed.
• Acoustical ceilings will be hung.
• Floor finishes will begin to be installed.
• Doors/hardware we be installed.
• Furniture will begin to be moved into classrooms.

Fun Fact: The polished concrete floor finish on the ground level of Alexia Hall requires low maintenance, is stain-resistant, and can be polished in ranges of low to high sheen in a variety of colors.

Alexia Hall skylight is installed

The skylight on Alexia Hall roof is installed

Bricks installation in Alexia Hall

A layer of thin brick is being installed on the 2nd floor of Alexia Hall

Christopher Hall lobby partition

A view behind the Christopher Hall lobby partition

Alexia Hall Entrance concrete being poured

Concrete being poured outside the Alexia Hall north entrance