Executive Summary Report June 26

Posted: June 26, 2014

What’s New?

Classrooms and offices are framed in the first phase of the LA remodel. The majority of Mechanical/Electrical/Plumbing in wall work has been completed. The concrete stage has been poured in the new commons building.

The Past Week

• Kitchen flooring is being installed.
• Framing in first phase of LA is complete.
• Fireproofing in N2 has started.
• Alexia Hall steel installation has begun.

Coming Up in the Weeks Ahead

• Kitchen equipment to be delivered the week of June 30.
• Rooms finishes will be installed in the first phase of LA.
• Porcelain tile to be installed in the new commons.
• Green roof to be installed over the new commons.
• Steel will continue to be set at Alexia Hall.

Did you know?

On a given day, there are up to 90 total workers on campus from over 15 different subcontractors.

Girders and concrete walls are being set

Steel Girders and Concrete Walls are Going Up!

Setting Steel for Alexia Hall

Alexia Hall Progress – Steel is Beginning to be Set.

Drywall Hanging, LA building

Drywall is being hung on LA-S 1st Floor.

New kitchen with hood and floor insets

Kitchen Progress – hoods and ceiling grid installed. Flooring installation has started.

Fire Proofing the new commons

Fire Proofing the New Commons Continues