PROJECT TIMELINE

Dates are subject to change. Bookmark promise & power for regular updates and current timeline information.

Executive Summary Report, June 5 2014

Posted: June 5, 2014

What’s New?

Alverno has moved out of the LA demolition locations, and the first phase of demo in the LA building has started. The first phase of LA includes first floor southwest, first floor north, and second floor north. Drywall is up in the kitchen, overhead mechanical/electrical/plumbing work continues.

Pouring the concrete slab for the new commons

Pouring of the concrete slab in the new commons has begun

Mechanical work in the kitchen continues

Kitchen progress – overhead mechanical work continues

The Past Week

• Above ceiling demolition in the first phase of LA is complete.
• Kitchen walls are primed and ready for finishes.
• Concrete slab pour began for new commons.
• Foundation work for Alexia Hall continues.

Coming Up in the Weeks Ahead

• Interior walls in the first phase of LA to be removed.
• New kitchen equipment to be delivered and installed.
• Interior framing to begin for new commons.
• Continue concrete work at Alexia Hall.

Fun Fact: As of May 23rd; 11,028 cubic yards of dirt have been exported from the campus.

foundation walls poured on Alexia hall

Alexia Hall progress – foundation walls are being poured

behind a containment wall in LA

A look behind the containment wall on LA-N 2nd floor

To learn more about how you can get involved in this transformational campaign for Alverno's future, please contact Kaye Leszczynski in the Advancement Office at (414) 382-6095 or kaye.leszczynski@alverno.edu. Thank you for your interest in and support of Alverno College!