PROJECT TIMELINE

Dates are subject to change. Bookmark promise & power for regular updates and current timeline information.

Executive Summary Report – March 27, 2015

Posted: March 27, 2015

What’s New?

The construction containment walls have been removed as work continues in the FO basement, 1st floor south, and 2nd floor south. Faculty move-in will begin on April 13th for the FO basement and the 1st and 2nd floor move-ins will follow 2-3 weeks later.

The Past Week

• Finishing touches are taking place in the FO basement.
• Ceilings and floors have been installed on the FO 2nd floor.
• Drywall and painting are complete on the FO 1st floor.

Coming Up in the Weeks Ahead

• Punch list work for FO basement, 1st floor south, and 2nd floor south.
• Completion/move-in for FO basement, 1st floor south, and 2nd floor south.
• Landscaping between Alexia Hall and the Commons.

Fun Fact: Construction is approximately 90% complete to date, and will be 100% complete in August 2015.

President's Office

FO 2nd Floor –President’s Office

Finance & Payroll office

FO 2nd Floor – Finance & MGT/HR & Payroll

Mail Services office in FO Basement

FO Basement – Mail Services

Book Sales office in FO Basement

FO Basement – Book Sales

To learn more about how you can get involved in this transformational campaign for Alverno's future, please contact Kaye Leszczynski in the Advancement Office at (414) 382-6095 or kaye.leszczynski@alverno.edu. Thank you for your interest in and support of Alverno College!