October 1 Executive Summary Report

Posted: October 1, 2014

What’s New?

With the first phase complete, the main focus of the project is Alexia Hall, which is scheduled to be complete in December ‘14.

The Past Week

• Library divider wall is completed.
• Work continues on the Heritage Wall.
• Interior concrete slabs have been poured at Alexia Hall.
• Exterior walls at Alexia Hall are framed and insulated.

Coming Up in the Weeks Ahead

• Masonry will begin at the Heritage Wall.
• Exterior masonry will begin at Alexia Hall.
• Roofing will begin at Alexia Hall.
• Work will begin on interior stairs & elevator at Alexia Hall.
• Exterior windows at Alexia Hall will be installed.

Fun Fact: Alexia Hall contains approximately 365,000 pounds of structural steel.

Alexia basment concrete being poured

Concrete being poured into the Alexia Hall basement

temporary heritage plaza

A look at the temporary Heritage Plaza

Duct work on Alexia Hall 2nd floor

Alexia Hall 2nd floor progress

library glass dividers

Library glass supplied by Tom Hovorka